2025–2026 Huzhou Tobacco Deqing Warehouse Facade Renovation Project

2025–2026 Huzhou Tobacco Deqing Warehouse Facade Renovation Project

Huzhou Tobacco Monopoly Bureau Deqing Cigarette Distribution Center · Color-steel tile renovation · Exterior wall panel renovation · Overall facade renewal

Color-steel tile renovation · exterior wall panel renovation · overall facade renewal.

Total renovation area ≈ 7,900 ㎡ | roof renovation ≈ 5,800 ㎡ | exterior wall panel renovation ≈ 2,100 ㎡ | duration 65 days | 12 high-altitude workers.

Project Overview

  • Project name: 2025–2026 Huzhou Tobacco Deqing Warehouse Facade Renovation Project
  • Location: Deqing County, Huzhou City, Zhejiang Province · Huzhou Tobacco Monopoly Bureau Deqing Cigarette Distribution Center
  • Contractor: Jixiu Building Tech (Jixiu Building Restoration Technology)
  • Scope: removal of old color-steel roofing and installation of new tiles; derusting and reinforcement of steel structure; removal of old exterior wall panels and installation of new panels; replacement of gutters and drainage; overall facade renewal
  • Main materials: 0.5 mm high-weathering color-steel tile; 50 mm glass-wool insulation; 0.4 mm fluorocarbon-coated exterior wall panel; 304 stainless self-tapping screws; hot-dip galvanized steel purlins
  • Key difficulties: warehouse must remain operational during renovation; large high-altitude roof area requiring strict edge protection; high precision required for waterproof detailing at old-new structure joints

Safety Measures

  • Dual-hook harness for high-altitude work: roof and exterior-wall workers wear dual-hook harnesses throughout, 'hook high, use low.'
  • Mobile scissor-lift platforms: 8–12 m self-propelled hydraulic scissor lifts with guardrails.
  • Roof edge protection: ≥1.2 m guardrails with posts ≤2 m apart and dense safety nets.
  • Site enclosure & warning: 2.0 m color-steel enclosure fully closes the work area with night warning lights.
  • Weather control: no high-altitude work in wind ≥ level 5, rain/snow, thunder; summer peak-heat shifted.
  • Certified personnel & pre-shift briefing: all high-altitude workers hold Work-at-Height certificates; 15-min safety briefing daily.
  • Temporary power three-level leakage protection: independent switch box per device, locked and managed by a dedicated person.
  • Hot-work & fire prevention: hot-work permits, fire extinguishers and fire pans; fire hoses and extinguishers on roof.

Construction Flow

  1. Demolish original roof/exterior wall — remove old tiles and panels in sections, centralized waste removal.
  2. Substrate inspection, derusting & reinforcement — blast-derust steel, epoxy zinc-rich primer + acrylic topcoat.
  3. Purlin installation & insulation — new galvanized purlins per drawing, spacing ≤1.5 m; lay 50 mm glass wool.
  4. New color-steel tile laying & seaming — 0.5 mm high-weathering tile with 360° standing-seam, lap ≥200 mm.
  5. Gutter & drainage replacement — replace stainless gutters and downpipes, verify slope.
  6. Exterior wall panel installation & trim — install fluorocarbon panels by grid lines, neat corner detailing.
  7. Overall acceptance & handover — water-spray test, waterproof-node check, appearance evaluation, then handover.

Project Highlights

  • Renewed overall appearance: blue roof + white walls, markedly improved corporate image.
  • Improved waterproofing: thoroughly solved chronic roof leakage, secure storage.
  • Enhanced corrosion resistance: new materials highly weather-resistant, service life extended to 15+ years.
  • Significant energy savings: high roof reflectivity + insulation, reduced summer cooling energy use.
  • Strict schedule control: delivered on time in 65 days without affecting warehouse operations.
  • Zero accidents: full high-altitude operation with no injuries or equipment accidents.

On-site Gallery

Project Highlights

  • Renewed appearance
  • Leakage solved
  • 15+ year lifespan
  • On-time delivery
  • Zero accidents

Need professional building restoration services?